If 10 workers complete a piece of work in 6 days by working 8 hours per day, how many workers are required to finish the work in 8 days by working 6 hours per day?
A
13
B
12
C
11
D
10
Correct Option:
D
Explanation
Total work:
10 × 6 × 8 = 480
New condition per worker:
8 × 6 = 48 hours
Thus,
480 / 48 = 10
So 10 workers are still required. The longer number of days exactly compensates for the shorter working day.