Twelve men can complete a work in 8 days. Three days after they started the work, 3 more men joined. In how many days will all of them together complete the remaining work?
A
2
B
4
C
5
D
6
Correct Option:
B
Explanation
Total work = 12×8 = 96 man-days. First 3 days consume 36, leaving 60. With 15 men, 60/15 = 4 days.