Skip to content
Home
›
HSSC Clerk Exams
›
2016-06-24 (24 Jun) (DAC)
Question 44 of 100
Question Palette
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
"A" can complete a piece of work in 12 days, and "B" can complete the same piece of work in 16 days. In how many days can "A" and "B" together complete the work?
A
5 1/3 days
B
6 3/7 days
C
5 2/3 days
D
6 6/7 days
Correct Option:
D
Explanation
A's rate = 1/12, and B's rate = 1/16. Together: 1/12 + 1/16 = 7/48. Time = 48/7 = 6 6/7 days.